Top Ten Construction Clauses - Part 3 - Liquidated Damages Provisions
This article is the third of a ten-part series analyzing ten critical construction
clauses. In this installment, we analyze
the “Liquidated Damages Provision.” The first two articles, which addressed the
indemnification clause and the mutual waiver of consequential damages clause,
can be found at: http://sotolawgroup.blogspot.com/2015/04/top-ten-construction-clauses-part-2.html
A liquidated damages provision determines in advance the measure of damages
if a party breaches the agreement. The
provision is most frequently utilized when a contractor fails to achieve
substantial completion of the construction project by the date set forth in the
contract. Two common reasons for using a
liquidated damages Provision are: (1) to avoid the difficulty and expense of
proving an owner’s actual damages attributable to a contractor’s failure to
achieve substantial completion on time; and (2) to incentivize the contractor
to stay on the project schedule.
The American Institute of Architects’ Agreement between the Owner and Contractor (AIA Document A101-2007) provides a space in Article 3 for insertion of a Liquidated Damages Provision. The AIA’s model Liquidated Damages Provision is set forth in its Guide for Supplementary Conditions (AIA Document A503-2007) and provides as follows:
II.
ENFORCEABILITY
IN FLORIDA
Before including a Liquidated Provision in a construction contract, one must carefully ensure that their liquidated damages provision is legally enforceable. In Florida, the court will not enforce a liquidated damages provision that it determines to be in the nature of a penalty. Where it is doubtful whether a contract provision constitutes a penalty or liquidated damages the tendency of the courts is to construe a provision for payment of an arbitrary sum a penalty rather than one for liquidated damages. T.A.S. Heavy Equip. v. Delint, Inc., 532 So. 2d 23, 25 (Fla. 4th DCA 1988) (citing Hyman v. Cohen, 73 So.2d 393 (Fla. 1954)). In making this determination, the courts will usually consider:
I.
OVERVIEW
The American Institute of Architects’ Agreement between the Owner and Contractor (AIA Document A101-2007) provides a space in Article 3 for insertion of a Liquidated Damages Provision. The AIA’s model Liquidated Damages Provision is set forth in its Guide for Supplementary Conditions (AIA Document A503-2007) and provides as follows:
The Contractor and
the Contractor’s surety, if any, shall be liable for and shall pay the Owner
the sums hereinafter stipulated as liquidated damages, and not as a penalty,
for each calendar day of delay after the date established for Substantial
Completion in the Contract Documents until the Work is substantially complete:
_______________ Dollars ($_________).
Before including a Liquidated Provision in a construction contract, one must carefully ensure that their liquidated damages provision is legally enforceable. In Florida, the court will not enforce a liquidated damages provision that it determines to be in the nature of a penalty. Where it is doubtful whether a contract provision constitutes a penalty or liquidated damages the tendency of the courts is to construe a provision for payment of an arbitrary sum a penalty rather than one for liquidated damages. T.A.S. Heavy Equip. v. Delint, Inc., 532 So. 2d 23, 25 (Fla. 4th DCA 1988) (citing Hyman v. Cohen, 73 So.2d 393 (Fla. 1954)). In making this determination, the courts will usually consider:
- The reasonableness of the provision;
- The certainty of establishing actual damages; and
- The intent of the parties.
See id. (citing
Refram v. Porter, 343 So. 2d 1343 (Fla. 2d DCA 1977). In the final analysis the test is whether the
damages flowing from the breach are readily ascertainable at the time the
contract is executed. See id. (citing South Florida Regional Planning
Council v. Board of County Commissioners of Palm Beach County, 372 So. 2d
1142 (Fla. 4th DCA 1979).
The most difficult element to establish, and therefore most important element,
is the first—the reasonableness of the provision. This test refers to the concept that the
liquidated damages must bear some relationship to the actual damages suffered.
To satisfy this objective, an owner wishing to include a liquidated damages
provision should carefully evaluate all aspects of damages it may suffer in the
event of delay such as lost profits and additional or increased financing
charges/interest. The number ultimately
included in the liquidated damages provision must be a product of this
analysis, not an arbitrary or punitive amount of money intended to penalize a
contractor.
Second, a liquidated damages provision will be unenforceable in the event that
the actual damages resulting from a contractor’s breach of contract were
readily ascertainable at the execution of the contract. Third, the intent of
the parties must indicate that the provision is not intended to be a
penalty. This can be achieved by
including language within the Liquidated Damages Provision that the amount of
liquidated damages is not intended as a penalty and that such amount has been
agreed upon due to the difficulty in determining the actual damages that will
be suffered by the Owner in the event of a failure to complete the work on
time.
III.
ADDITIONAL
CONSIDERATIONS
A contractor concerned with the risk of accepting
a Liquidated Damages Provision has a few options to limit or offset such
exposure. For example, a contractor may insist on the inclusion of an early
completion bonus as compensation for the additional risk involved in a
liquidated damages provision. In
addition, a contractor should include liquidated damages provisions in its
contracts with subcontractors so that it can properly pass through liquidated
damages to the responsible parties.
Finally, owners should consider whether the
benefits of including a liquidated damages provision in its contracts outweigh
the risks. For example, including such a provision may encourage a hostile
working relationship with the contractor, who may feel the need to notify the
owner in writing each time it believes the owner has contributed to a delay on
the project. In addition, a contractor
who is aware that a liquidated damages provision will be included in the
contract may be encouraged to submit a project schedule that is longer that the
contractor actually anticipates so that it can begin the Project with a
built-in cushion.
Consult with an attorney knowledgeable in construction so that together you can
decide whether it is advisable to include a liquidated damages provision in
your contracts.
BY: DALE A. EVANS JR., ESQ.
The Soto Law Group, P.A.
2400 E. Commercial Blvd.,
Suite 400
Fort Lauderdale, FL 33308
dale@sotolawgroup.com
TEL: 954-567-1776
FAX: 954-567-1778
The hiring of a lawyer is an important decision that should not
be based solely upon advertisements. Before you decide, ask us to send you free
written information about our qualifications and experience. Additionally, the
information above is not intended to be legal advice. Please consult with an
experienced lawyer if you have a specific issue or dispute.