TOP TEN CONSTRUCTION CLAUSES - PART IX - PAYMENT TERMS
TOP TEN
CONSTRUCTION CLAUSES – PART IX – PAYMENT TERMS
This article is the ninth in a
ten-part series analyzing the top ten critical construction clauses. In this installment, we analyze the “payment
terms” provision, which encompasses a discussion on retainage and final payment. This article will focus primarily on the
updated American Institute of
Architects’ Agreement between the Owner and Contractor (AIA Document A101-2017)
as well as Florida case law.
I.
OVERVIEW
The payment terms provision is
perhaps the most palpable of all construction clauses as each party to a
construction contract has unique concerns when it comes to payment. An owner is concerned about overpaying its
general contractor before its work is completed and will require some kind of
assurance that the work will be completed.
Meanwhile, a general or subcontractor is concerned about receiving prompt
payment so not to create financial hardship.
In negotiating the terms of payment, the goal is to reach a balanced
resolution of all concerns.
II.
PAYMENT
PROCEDURES
The American
Institute of Architects’ Agreement between the Owner and Contractor (AIA Document
A101-2017) attempts to find this balance by incorporating monthly progress
payments based upon applications for payment submitted to the owner after being
reviewed and approved by the architect. The
AIA form provides that prior to any application for payment being submitted,
the contractor must first submit an itemized schedule of values for the
architect’s approval. The schedule of
values allocates a line item value for various items of work. An application for payment will typically
list each item on the schedule of value and provide the percentage complete
along with the value of the completed work.
The architect is tasked with reviewing the payment application and
signing off on it. The owner is then
responsible for making the determined payment minus any retainage. The owner’s failure to make payment in
accordance with the contractual requirements constitutes a material breach of
contract. See J.M. Beeson Co. v.
Sartori, 553 So. 2d 180 (Fla. 4th DCA 1989); see also Newkirk
Construction Corp. v. Gulf County, 366 So. 2d 813 (Fla. 1st DCA
1979).
III.
TIMING OF
PAYMENT
Under Florida’s Construction
Contract Prompt Payment Law, any party with an obligation to make payments
under a written construction contract must make the payments promptly once
certain conditions have been met. Fla.
Stat. §715.12(4) (2017). The law
generally provides that, unless some exception exists, the obligor has 14 days
to make payment to the obligee otherwise the payment due will bear interest at
the statutory rate. Fla. Stat. §715.12(5)(a) (2017).
With this in mind, AIA Document
A101-2017 provides a form provision that leaves it to the contracting parties
to set their own deadlines for payment.
The relevant provision reads as follows:
Ҥ 5.1.3 Provided that an Application
for Payment is received by the Architect not later than the ______ day of a
month, the Owner shall make payment of the amount certified to the Contractor
not later than the _____ day of the month.
If an Application for Payment is received by the Architect after the
application date fixed above, payment of the amount certified shall be made by
the Owner not later than _____ ( )
days after the Architect received the Application for Payment.”
IV.
RETAINAGE
& FINAL PAYMENT
As previously mentioned, the owner
has an interest in ensuring there are sufficient funds to complete the
contractor’s scope of work in the event the contractor fails to do so. Hence, it is common for contracts to provide
for retainage, commonly 10% of the contract amount, of each payment
application. The retainage is held by
the owner until the contractor reaches some pre-defined stage of construction
and all other conditions have been met.
The American
Institute of Architects’ General Conditions of the Contract for Construction is
incorporated into AIA A101-2017 by reference.
Section 9.10.2 of the General Conditions contains contractual conditions
that the contractor must satisfy in order to receive final payment of the
retainage. Specifically, the contractor
is required to submit to the architect 1) proof that all payrolls, bills for
materials and equipment, and other indebtedness connected with the work for
which the owner or the owner’s property might in any way be responsible have
been paid or satisfied, 2) written proof that all insurance required by the
contract is in effect and will remain in effect unless written notice is
provided 30 days in advance, 3) a written statement that the contractor knows
of no reason why the insurance will not be renewable to cover the period
required by the contract, 4) written proof of any surety’s consent to final
payment, and 5) any additional data that the owner requires to establish the contractor’s
payment or satisfaction of all contractual obligations.
Under
the AIA, contractors must be conscience of the General Conditions §
9.10.5 which provides that once the contractor accepts final payment it is
deemed to have waived all claims not previously made in writing and identified
by the contractor as unsettled at the time of the final payment application.
It is important to note that you may encounter non-AIA
form contracts. Regardless
of the form used in drafting any construction contract, the payment terms
provision should be concisely drafted and touch on all the basics discussed
above to reduce ambiguity. Whether you
are an owner, contractor or subcontractor, it is advisable to consult with
an attorney knowledgeable in construction contracts to assist you in deciding
what payment terms are best suited for your business.
Comments
Post a Comment