TOP TEN CONSTRUCTION CLAUSES - PART VII - NO DAMAGES FOR DELAY
PART VII—NO
DAMAGES FOR DELAY
This is the seventh installment in a ten-part series analyzing critical construction clauses. This installment analyzes the “No Damage for Delay” provision. My first six articles can be found on our blog at http://sotolawgroup.blogspot.com/.
A.
Overview
and Background
Most construction contractors and
subcontractors assume that if they encounter a delay on the project that is not
attributable to them, for example, changes in the sequencing of the work
ordered by the project owner, discovery of hazardous materials or unknown
conditions at the project, or adverse governmental actions, that they would
entitled for reimbursement for damages caused by those delays. Such damages
could include unabsorbed home office overhead, remobilization/acceleration
costs, or increased materials costs.
However, an increasingly common contract
provision, known as the “No Damages for Delay Provision” bars recovery of these
damages and poses a substantial risk. It is important to recognize a “No Damage
for Delay” provision in a potential contract, understand how and when such a
provision can be enforced, and how to protect yourself if such a provision is
included in your contract.
B.
Sample
“No Damage for Delay” Provision
Neither the American Institute of Architects
nor ConsensusDocs—two of the foremost authorities on construction
contracting—contain a model “No Damages for Delay” provision in their form
contracts between owners and general contractors. In fact, both expressly
authorize recovery of damages caused by delay.
A sample provision previously used by Broward
County that was the subject of an oft-cited Florida appellate court opinion
(discussed in further detail below) is:
NO CLAIM FOR DAMAGES OR ANY CLAIM OTHER THAN
FOR AN EXTENSION OF TIME SHALL BE MADE OR ASSERTED AGAINST THE COUNTY BY REASON
OF ANY DELAYS. The CONTRACTOR shall not be entitled to an
increase in the Contract Sum or payment or compensation of any kind from the
COUNTY for direct, indirect, consequential, impact or other costs, expenses or
damages, including but not limited to costs of acceleration or inefficiency,
arising because of delay, disruption, interference, or hindrance from any cause
whatsoever, . . . ; provided, however, that this provision shall not preclude
recovery or damages by the CONTRACTOR for hindrances or delays due solely to
fraud, bad faith, or active interference on the part of the COUNTY or its
agents. Otherwise, the CONTRACTOR shall be entitled only to extensions of the
Contract Time as the sole and exclusive remedy for such resulting delay, in
accordance with and to the extent specifically provided above.
Triple
R Paving, Inc. v. Broward County, 774
So. 2d 50 (Fla. 4th DCA 2000).
C.
“No
Damage for Delay” provisions are generally enforceable, but beware of
exceptions.
As you can see from the “No Damage for
Delay” provision in the Triple R Paving case,
these provisions are typically extremely broad and insulate the owner (or
upstream contractor) from a wide array of damages that would be otherwise
recoverable. Although clauses providing for “no damages for delay” are generally
enforceable, there are a couple of important exceptions. For example, the
courts in Florida have found that “No Damages for Delay” provisions are invalid
in cases of fraud, bad faith, or active interference by the owner. See Triple R Paving, 774 So. 2d at 54.
In Triple
R Paving, the appellate court found that the contractor submitted
sufficient proof that the county’s engineer knew that his plans did not meet
horizontal sight distance standards but failed to notify the contractor,
despite the fact that the engineer personally agreed to check the sight
distance against standards at the time in question. The court found that the
facts submitted in support of this claim were sufficient to allow a jury to
decide the question of fraud, bad faith, or active interference, despite the
existence of an otherwise enforceable “No Damages for Delay” provision.
Newberry
Square Dev. Corp. v. Southern Landmark, Inc., 578 So. 2d 750 (Fla. 1st DCA
1991) involved an even more egregious example of active interference, leading
the court to invalidate the “No Damages for Delay” provision. In that case, the
contractor submitted evidence that the developer delayed in providing approved
plans and specifications, delayed in executing change orders and required that
construction not proceed without such orders. It was also indicated that the
developer repeatedly failed to make timely payments required by the contract.
Most significantly, the contractor testified that the developer actually
threatened that “he would break me before he’d pay . . . .” Under these
circumstances, the court held that there was adequate evidence to present a
jury question as to whether the developer actively impeded, or willfully and
knowingly delayed, the contractor’s ability to timely perform under the
contract, and in those circumstances, the “No Damages for Delay” provision did
not preclude the contractor’s recovery.
D. Conclusion
The “No Damage for Delay Provision” is an
effective tool for the owner (or any upstream contractor) to limit exposure to
damages caused by unforeseen or unexpected project delays. These protections,
however, are not absolute and the owner should ensure that its conduct complies
with the implied duties of good faith and fair dealing that are applicable to
every contract. Otherwise, the “No Damages for Delay” provision may be
invalidated based upon one of the well-established exceptions.
A contractor (or downstream subcontractor)
should avoid the “No Damages for Delay” provision where its bargaining position
enables contract negotiation. If a contractor cannot eliminate the provision,
it should ensure that all of its downstream contracts contain the provision so
that it is not liable for damages to its subcontractors that it cannot recover
from the owner.
In addition, a contractor (or downstream
subcontractor) must comply with the notice provisions of the contract to be
entitled to an extension of time or damages (in the event that the “No Damages
for Delay” provision is invalid). See,
e.g., Marriott Corp. v. Dasta Constr. Co., 26 F.3d 1057 (11th Cir. 1994). In
Dasta Construction, the 11th Circuit
held that the contractor’s failure to avail itself of its right to request an
extension of time based on project delays precluded it from recovering for
damages, even for delays allegedly
resulting from the property owner’s active interference. Accordingly, it is
critical that the contractor adheres to the notice requirements of the
contract, which often requires written notice served in a particular manner
within a short period of time after discovery of the delay.
The foregoing is not meant to be an exhaustive discussion of the “No
Damages for Delay” Provision and is intended only as a general primer regarding
some of the primary issues involving this clause. Consult with an attorney
experienced in drafting “No Damage for Delay” provisions so that together you
can negotiate a provision suitable for your business.
Comments
Post a Comment